11 |
River Research Institute (RRI), Faridpur. |
Morphological and Hydro-Biological Survey for Arial Khan river at Chandrapara, Sadarpur, Faridpur under River Research Institute (RRI), Faridpur during the year 2019-20. |
Completed |
January to June, 2020. |
12 |
River Research Institute (RRI), Faridpur. |
Morphological and Hydro-Biological Survey for Kalivodra river a Kharnia Bazar & Chandgaon, Khulna under River Research Institute (RRI), Faridpur during the year 2019-20 |
Completed |
August, 2020 to June 2021. |
13 |
Barishal O&M Division, BWDB, Barishal. |
Survey for Bank Protection and Dredging work of the Kirtonkhola, Joyonti, Arial Khan, Sondhya, Sugondhya, Ashokathi, Otra and Torki Branch River at different location & Khal Re-excavation under Barishal O&M Division, BWDB, Barishal during the year 2019-20. |
Completed |
April to June, 2020. |
14 |
Bagerhat O&M Division, BWDB, Bagerhat. |
Pre-work survey work in 18 Nos khal Length = 52.700 km ic/w "Rehabilitation of Polder no. 36/1 in Bagerhat District (1st revised)" under Bagerhat O&M Division, BWDB, Bagerhat (Contract Package No.: RFQ-S/02). |
Completed |
March to June, 2020. |
15 |
Bagerhat O&M Division, BWDB, Bagerhat. |
Pre-work & Post-work survey for Different Rivers/ Khals ic/w "Rehabilitation of Polder no. 36/1 in Bagerhat District (1st revised)" under Bagerhat O&M Division , BWDB , Bagerhat (Contract Package No.: RFQ-07/36/1/2019-20). |
Completed |
March to June, 2020. |
16. |
PGCB, GMD-Mymensingh. |
Bathymetric Survey & Morphological analysis of Dhanu river under Office of the Executive Engineer, GMD-Mymensingh, PGCB. |
On going |
January, 2020. |
17. |
Bhola O&M Division-2, BWDB, Charfesson, Bhola |
Survey of Meghna river for determining rivers bed Level in the Polder No.: 56/57 in connection with “Protection of different important bazar, Pourasava, Town and Polder embankment from the Erosion of Meghna River in Bhola District” during the year 2019-20 (Packae No.: Poura-Char-01/2019-2020). |
Completed |
January to June, 2020. |
18. |
Sirajgonj O&M Division, BWDB, Sirajgonj. |
Bathymetric Survey in the Jamuna river in connection Sirajgonj Hard point monitoring during monsoon’2020 (July to October’ 2020) during the year 2020-21. |
Completed |
July to October, 2020. |
19. |
Hobigonj O&M Division, BWDB, Hobigonj. |
Bathymetric survey of Kushiara river from Km 0.000 to 5.000 & Dhaleshwari river from Km 0.000 to Km 15.100 Total 20.100 at Upazilla Nabiganj & lakhai Dist. Habiganj under NDR budget under Habiganj O&M Division BWDB Habiganj during the year 2020-2021 |
Completed |
November, 2020. |
20. |
Elite Trading Ltd., Dilkusha, Dhaka. |
Bathymetric Survey work in the Tentulia rivers in connection with dredging volume calculation & progress monitoring work. |
Completed |
January to December, 2020. |